Progress Continues at Tondo Halfway House


The structure continues to take shape in Tondon, and major milestones continue to be accomplished. A few recent updates from October and November include:

  • Agreement has been achieved with Meralco, Manila’s power supplier, to remove the dangerous power mast in front of the Half-Way House
  • Structural work on the lower floors is now 75% completed
  • Preparations for the 4th floor are also completed and the concrete is poured
  • All structural works should be finished by Xmas
  • Member of the Board Hugo Banziger will visit SMDP and the Tondo construction site over the Christmas holidays, so look for more updates soon.